Robert Kirschman, Planner, provided a presentation that included the following:
- Purpose
- Location Map
- Circulation
- Site Plan
- Proposed Architecture
- Neighborhood Meeting/Public Input
- Recommendation
Member Linton questioned what the in-lieu fee covers.
David Laws, Permitting Manger, responded that the theory behind the in-lieu fee is to collect monies from the developer to hold in an account. Somewhere down the road should the decision be made to make improvements along Oracle Road the funds would be available.
Keri Silvyn, Lazarus, Silvyn & Bangs, P.C. representing the master developer, Evergreen, LLC. provided a presentation that included the following:
- Background on the project
- Vision for mixed use development
- Developed in phases
- Traffic circulation
Matt Stuart, Cypress civil development, representing the developer, provided a presentation that included the following:
- Overview of the project
- Basis circulation drop-off
- Hours of operation
- Bicycle parking
- Trash enclosure
Ricky Lyons, Developer, provided an overview on the drive thru and included the following:
- 30-35% of business is done through the drive-thru
- The longest drive-thru he has been associated with
Kevin Nguyen, Galloway Architects, provided a presentation that included the following:
- Complementary with Steam Pump
- Complementary colors
- Material Board
MOTION: A motion was made by Nathan Basken, Member and seconded by Sarah Chen, Member to Recomend Approval of the Conceptual Site Plan finding that the request is in conformance with the Design Principles and Steam Pump Village Design Guidelines, subject to the condition the applicant explore alternative location for the trash enclosure prior to Final Site Plan.
MOTION carried, 6-1 with Hal Linton, Member opposed.
MOTION: A motion was made by Nathan Basken, Member and seconded by Jacob Herrington, Member to Recomend Approval of the Conceptual Architecture finding that the request is in conformance with the Design Principles and Steam Pump Village Design Guidelines.
MOTION carried, 7-0.
Robert Kirschman, Planner, provided a presentation that included the following:
- Purpose
- Location map
- Proposed Site Plan
- Proposed Architecture
- Neighborhood Meeting/Public Input
- Recommendation
Applicant had no presentation.
MOTION: A motion was made by Jacob Herrington, Member and seconded by Kit Donley, Member to Recomend Approval of the Conceptual Architecture finding that the request is in conformance with the Design Principles and Steam Pump village Design Guidelines.
MOTION carried, 6-1 with Sarah Chen, Member opposed.
Michael Spaeth, Senior Planner, provided the following Planning Update:
- July 12, Conceptual Design Review Board Agenda
- July 6, Town Council Agenda
- June 30, Vistoso Highlands Major General Plan Amendment Neighborhood Meeting